Annual report - 2020

2021-03-31

Annual report for the period 1 January – 31 December 2020

During a year characterized by Covid-19, the development of existing projects has continued largely according to plan, and despite the pandemic, we have managed to establish ourselves in the US market without being physically in place. We have taken a major step towards our aim of becoming a leading investor in geothermal energy production.

The result of - SEK 71.3 million compared with +2.5 SEK in 2019 is partly due to the strengthened krona which affected the result by - SEK 22.8 million. Despite the fact that the business has developed positively and the shares in the portfolio companies have increased in value in local currency, this means a net write-down of SEK 6.9 million. Furthermore, interest expenses increased by SEK 22.9 million compared with the previous year, of which interest expenses for the bond accounted for SEK 13.2 million. The interest rate has been unchanged during the year and the increased cost is due to the company paying interest for 12 months in 2020, but in 2019 only for parts of the year. The remaining increase in interest expenses is attributable to increased loans from the parent company and ultimately the company's owners. The negative result is also an effect of the company choosing to be conservative in the valuation of ongoing projects.

In 2020, we have, among other things:

  • Commissioned two power plants in Japan. At the end of April, the first project, Waita, was commissioned. At the beginning of June, the second power plant, Midori, was commissioned. Ryuta Hiratsuka was hired as the new CEO of Baseload Power Japan after Ito Masahiro.
  • Continued work on a number of projects in Taiwan. Drilling began at the end of August for the Westlake project, which is expected to be the first commercial geothermal project in Taiwan. The project development was delayed due to some of the drilling equipment getting stuck in the drilling pipe at a depth of 630 meters, but is now up and running.
  • Converted the convertible loan issued by Baseload Capital to the Icelandic company Varmaorka. The new shares make Baseload the largest owner in the company. Varmaorka commissioned Reykholt's power plant, which will supply 300 kW to the electricity grid. A new cooling system was installed at the Fludir power plant, which is expected to reduce internal electricity consumption by up to 15%.
  • Established a subsidiary in the US, Baseload Power US. The company began investing in a first project in California by acquire contracts and equipment from the existing owner. Commissioning of the power plant is expected to take place during the second half of 2021. Three land lease agreements were signed in Nevada, where there is great potential for the development of new geothermal projects.
  • Initiated a collaboration with the New Zealand company Geo 40. Baseload participated in the new issue carried out by Geo40 during the year. Geo40 has developed a technology for extracting silicon and other minerals from geothermal water, which reduces the operating costs of geothermal power plants. At the same time, minerals are produced in a sustainable way.
  • Renegotiated and changed the terms of the green bond that the company issued during the first quarter of 2019 to better suit the company's business model. The first money was deducted from the bond. All covenants that the company must live up to were met during all quarters of 2020. In May, the bond was listed on Nasdaq.
  • Strengthened liquidity by the parent company Baseload Capital Holding AB raising a convertible loan of SEK 94.2 million from the main owners during the year.

The information was submitted for publication at 19:00 CET on 31 March 2021.

For more information, please contact:
Alexander Helling CEO of Baseload Capital
alexander.helling@baseloadcap.com

RELATED POSTS

「我們的隱藏力量」- 全台第一本地熱與再生能源童書發表

台灣台北(西元2023年7月10日)– 來自瑞典的兒童繪本 ”Our Hidden Powers” 正式發表繁體中文版 –「我們的隱藏力量:風光水火土  打造永續地球」

倍速羅得串連公學研   深耕地熱能源教育   為台灣打造關鍵人才基地

台灣台北(西元2023年5月18日)– 邁向淨零永續轉型,地熱能源為關鍵戰略之一,瑞典地熱能源開發商倍速羅得公司(Baseload Power Taiwan)今(18日)攜手8所地質與地球科學領域公學研單位,

地熱能源開發商倍速羅得攜手花蓮紅葉國小,齊力守護太魯閣族歌謠樂舞與文化傳承

花蓮縣萬榮鄉紅葉國小近年翻轉教育思惟,不囿於偏鄉匱乏,不盲目追求第一,重塑傳統文化課程,帶領孩子看見所處的美好土地與文化瑰寶,以作為獨一無二的部落後代,感到榮耀與自信。地熱能源開發商倍速羅得來自尊重多元文化價值的瑞典,因地熱發電計畫與紅葉部落結緣,深感認同校方以文化培育內在韌性的教育理念,於10月30日親子運動會活動中,黃天德董事長親自出席並捐贈10萬元教育基金,以實際行動支持文化紮根教育,展現深耕在地、與社區共好之心意,期望與學校、部落與地方政府共同合作,打造文化傳承平台,齊力守護太魯閣族歌謠樂舞與文化。
1 2 3 ... 8
menuchevron-down linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram